EXPERIENCE

2023
– Senior Offshore Quality Control Specialist on Moray West Wind Farm. (60 14.7MW DD SGRE Turbines)
  Production, Pre-assembly, Installation, Commissioning and handover.
– Quality and fabrication engineer for ParkWind on Arcadis ost 1 (27 V174. 9.5MW)
– Site manager onsite Main Component Exchange for Vattenfall.
– Consultancy for the Zhong Neng 300MW offshore project in Taiwan.
– Design and fabrication of prototypes for Danwind Spareparts.
– Design and fabrication of prototypes for Ørsted.
– Consultancy for Danwind Construction on various projects on Installation, and commissioning.
– Consulting international green energy investors on Installation, and commissioning.
– Consultancy for Zülau on various projects.

2022
– Quality and fabrication engineer for ParkWind on Arcadis ost 1 (27 V174. 9.5MW)
– Site manager onsite Main Component Exchange for Vattenfall.
– Quality and fabrication engineer for Macquarie Capital on Formosa ll (47 SG 8.0-167 DD WTG’s)
– Offshore Wind Farm in Taiwan.
– Consultancy for Macquarie Capital on Formosa 1 Phase II and Formosa 2.
– Design and fabrication of prototypes for Danwind Spareparts.
– Design and fabrication of prototypes for Ørsted.
– Consultancy for Danwind Construction on various projects on Installation, and commissioning.
– Consulting international green energy investors on Installation, and commissioning.
– Consultancy for Zülau on various projects.

2021
– Quality and fabrication engineer for Macquarie Capital on Formosa ll (47 SG 8.0-167 DD WTG’s)  Offshore Wind Farm in Taiwan.
– Consultancy for Macquarie Capital on Formosa 1 Phase II and Formosa 2.

2020
– Quality and fabrication engineer for Macquarie Capital on Formosa ll (47 SG 8.0-167 DD WTG’s)
Offshore Wind Farm in Taiwan.
– Consultancy for Macquarie Capital on Formosa 1 Phase II and Formosa 2.
– Design and fabrication of prototypes for Danwind Spareparts.
– Joint venture with Asia Renewable Management. www.arm-th.com
– Consultancy for Envision on various projects on Installation, and commissioning.
– Consulting international green energy investors on Installation, and commissioning.
– Design and fabrication of prototypes for Fritz Schur Teknik A/S
– Consultancy for EON on various projects.
– Consultancy for Zülau on various projects.

2019
– Installation,commissioning and QA manager for Formosa Wind Power Co.
– Installation and commissioning of 20.  6.0MW Siemens DD wind turbines. 
– Consultancy for the owner of the GT 1 projects. 
– Design and fabrication of prototypes for Danwind Spareparts.
– Consultancy for Envision on various projects on Installation, and commissioning.
– Joint venture with Asia Renewable Management (www.arm-th.com)
– Consulting international green energy investors on Installation, and commissioning.
– Design special toolsets for GE Wind Energy
– Design special toolsets for Adwen
– Design and fabrication of prototypes for Fritz Schur Teknik A/S
– Consultancy for Vattenfall on various projects.
– Consultancy for EON on various projects.
– Consultancy for Ørsted on various projects.
– Consultancy for Zülau on various projects.

2018
– Design and fabrication of prototypes for Danwind Spareparts.
– Started joint venture with Asia Renewable Management.        www.arm-th.com
– Consulting international green energy investores on Installation, and commissioning.
– Design special toolsets for GE Wind Energy.
– Design special toolsets for Adwen.
– Design and fabrication of prototypes for Fritz Schur Teknik A/S.
– Consultancy for Vattenfall on various projects.
– Consultancy for EON on various projects.
– Consultancy for Ørsted on various projects.
– Consultancy for Zulau on various projects.

2017
– Consulting international green energy investores on Installation, and commissioning.
– Design special toolsets for GE Wind Energy.
– Design special toolsets for Adwen.
– Project Vaje Mate.
– Site manager pre-assembly on Esbjerg harbour for Øer A/S.
– Pre-assembly and commissioning of 67 Siemens D6.
– Design and fabrication of prototypes for Fritz Schur Teknik A/S.
– Consultancy for Vattenfall on various projects.
– Consultancy for EON on various projects.
– Consultancy for Ørsted on various projects.
– Consultancy for Zulau on various projects.

2016
– Project Vaje Mate.
– Site manager pre-assembly on Esbjerg harbour for Øer A/S.
– Pre-assembly and commissioning of 67 Siemens D6.
– Design and fabrication of prototypes for Fritz Schur Teknik A/S.
– Design special toolset for transformer repair for VB Enterprise.
– Consultancy for Vattenfall on various projects.
– Consultancy for DONG on various projects.
– Consultancy for Siemens Wind Power on various projects.
– Consultancy for VB-Enterprise on various projects.
– Development of tool solutions for the wind industry.
– Consultancy for Zulau on various projects.

2015
– Design and fabrication of special flange alignment tool set, for monopile and
TP installation on Sandbank 24.
– Design and fabrication off complete auxiliary tool set, for offshore transformer
change, for Siemens Wind Power.
– Development of tool solutions for the wind industry.
– Consultancy for Zulau on various projects.

2014
– Marine Serveyor on project Butendiek.
– Inspector for DNV-GL.
– WindMW Project Meer Wind.
– Site and Quality Management for Siemens Wind Power.
– Project Burkum Riffgat.
– Site management on Mock-up for DONG Energy Wind Power.
– Member of the enginering group developing the new 4MW for Siemens Wind Power.
– Member of the enginering group developing the new 6MW for Siemens Wind Power.
– Development of tool sulutions for the wind industry.
– Consultancy for Zulau on various projects.

2013
– ProjectLondon Array Ltd
– Site & Quality Management for Siemens Wind Power.
– On the largest offshore wind farm in the world, London Array.
– WindMW Project Meer Wind.
– Site and Quality Management for Siemens Wind Power.
– Project Lincs Project.
– Site Management on repair work for Siemens Wind Power.
– Project Westermost Rough.
– Site Management on 6MW complete bottom tower Mock-up for Siemens Wind Power.
– Project Woods.
– Site Management on complete Power cable Mock-up.
– Member of the enginering group developing the new 4MW for Siemens Wind Power.
– Member of the enginering group developing the new 6MW for Siemens Wind Power.
– Development of tool sulutions for the wind industry.
– Consultancy for Zulau on various projects.

2012
– London Array Ltd
– Site & Quality Management for Siemens Wind Power.
– On the largest offshore wind farm in the world, London Array.
– Development of tool sulutions for the wind industry.
– Member of the enginering grup developing the new 4MW for Siemens Wind Power.
– Consultancy for Zulau on various projects.

2011
– London Array Ltd
– Site & Quality Management for Siemens Wind Power.
– On the largest offshore wind farm in the world, London Array.
– Development of tool sulutions for the wind industry.
– Consultancy for Zulau on various projects.

2010
– Site Management for Siemens Wind Power.
– On the largest offshore wind farm in the world, London Array.
– Site manager for DanRun Windservice in Japan, for EBARA Corporation.
– Development of tool sulutions for the wind industry.
– Consultancy for Zulau on various projects.

2009
– Site Manager for DanRun Windservice in Japan, for EBARA Corporation.
– Consultancy for CMC A/S, on building a new kind of offshore installation Wessel.
– Site manager on a warranty repair, for Suzlon, in Brazil.
– Supervision on repair and maintenance work for DWS-Wincon.

2008
– Senior Supervisor on repair and maintenance work for DWS-Wincon.
– Project Management for NBT AS China.
– Complete planning of all installation, on the 200MW Baicheng Wind Farm, in China.

01-07-2007 – 10-08-2007
– Senior Site Supervisor For Total Wind A/S
– (France) Freelance Site manager.
– 36MW wind farm for Eole-Res Coordination of turbine erection, management of the turbine
outfit energisation and commissioning.
– Installing software and training of client’s staff in the day to day operation.

01-04-2007 – 01-06-2007
– Senior Site Supervisor For Siemens Wind Power (UK)
– 90MW Off shore wind farm for DONG Coordination of turbine erection, management of the
turbine outfit, energisation and commissioning.
– Training of all Siemens technicians in all aspects of WTG work. Training of client’s staff in the
day to – day operation of the turbines. Installing software and training of clients in operation.
– Supervise installation, commissioning, handover, maintenance and troubleshooting both for
– Siemens – technicians and the client’s personnel.

01-11-2006 01-04-2007
– Senior Site Supervisor For Siemens Wind Power (Scotland)
– 19MW Wind farm for Scottish Power Coordination of turbine erection, management of the
turbine outfit, energisation, commissioning & handover.
– Training of all Siemens technicians in all aspects of WTG work. Training of client’s staff in the
day to – day operation of the turbines.
– Installing software and training of clients in operation.

– Supervise installation, commissioning, handover, maintenance and troubleshooting both   for Siemens – technicians and the client’s personnel.

01-03-2006 30-09-2006
– Senior Site Supervisor For Siemens Wind Power (France)
– 40MW Wind farm for Eole-Res Coordination of turbine erection, management of the turbine
outfit, energisation and commissioning & handovr.
– Training of all Siemens technicians in all aspects of WTG work. Training of client’s staff in the
dayto – day operation of the turbines.
– Installing software and training of clients in operation.
– Supervise installation, commissioning, handover, maintenance and troubleshooting both
for Siemens – technicians and the client’s personnel.

25-10-2005 02-02-2006
– Senior Site Supervisor For Siemens Wind Power (Germany)
– 20MW Wind farm for AN Wind Coordination of turbine erection, management of the turbine
outfit, energisation, commissioning & handover.

17-08-2005
– Senior Site Supervisor For Siemens Wind Power (Austria)
– 13MW Wind farm for EKO Wind Coordination of turbine transport, erection, management
of the turbine outfit, energisation, commissioning & handover.

11-07-2005 16-08-2005
– Training Siemens Wind Power.

30-03-2005 10-06-2005
– Senior Site Supervisor for Nordex (France)
– Daily operation of all Nordex turbines in France (9 Wind farms 70 MW)
– Training of all Nordex technicians in all aspects of WTG work. Training of client’s staff in the day – to – day operation of the turbines. Installing software and training of clients in operation.
– Supervise installation, commissioning, handover, maintenance and troubleshooting both for
– Nordex technicians and the client’s personnel.

01-01-2005 29-03-2005
– Senior Site Supervisor for Nordex (China)
– Have just achieved take-over of Faku Wind farm 10 MW plant for (Faku Dong Fang)
– Daily operation of all Nordex turbines in China (12 wind farms 105MW)
– Training of all Nordex technicians in all aspects of WTG work. Training of client’s staff in the
day to – day operation of the turbines.
– Installing software and training of clients in operation.
– Supervise installation, commissioning, handover, maintenance and troubleshooting both for
– Nordex technicians and the client’s personnel.

01-01-2004 31-12-2004
– Senior Site Supervisor for Nordex (Greece)
– Daily responsibilities as above on 4 Wind farm sites 46 turbines – 30 MW)
– Training of all Nordex technicians in all aspects of WTG work. Training of client’s staff in th
day to – day operation of the turbines.
– Installing software and training of clients in operation.
– Supervise installation, commissioning, handover, maintenance and troubleshooting both for
– Nordex technicians and the client’s personnel.
– Fullfilled final – commissioning / Maintenance contract to satisfaction of client
(Energy 2 and – Thanassis Karadimas)

01-10-2003 31-12-2003
– Senior Site Supervisor for Nordex (China)
– Daily operation of all Nordex turbines in China (12 wind farms 105MW)
– Training of all Nordex technicians in all aspects of WTG work. Training of client’s staff in the
day to – day operation of the turbines. Installing software and training of clients in operation.
– Supervise installation, commissioning, handover, maintenance and troubleshooting both for
– Nordex technicians and the client’s personnel. Achieved take over to satisfaction of – client.

01-07-2003 01-10-2003
– Senior Site Supervisor for Nordex (Scotland)
– 50MW Wind farm for Fred Olsen Renewables, coordination of turbine erection, management
of the turbine outfit, energisation, commissioning & handover.

01-04-2003 01-07-2003
– Senior Site Supervisor for Nordex (France)
– Daily operation of all Nordex turbines in France (9 Wind farms 70 MW) Supervise installation,
commissioning, training, handover, maintenance and troubleshooting both for Nordex
technicians and the client’s personnel.

01-06-2002 01-04-2003
– Supervisor for Nordex (Portugal)
– Supervise gearbox overhaul of Nordex turbines.

01-01-2000 01-06-2002
– Supervisor for the Nordex packing division DK (Denmark)
– Manager for packing and sending all equipment for new projects all over the world.

01-12-1996 01-01-2000
– Supervisor for Nordex (Denmark, Sweden, Germany)
– Installation, commissioning, and repair/maintenance of turbines.

1996 (for eight month)
– Supervisor (Kalgoorlie – W. Australia)
– Mechanical and Electrical repairs/maintenance to all types of machinery in the gold
mining industry.

01-11-1994 01-03-1996
– Subcontractor Technician for Sawo Hydraulic (Denmark)
– Worked as a technician, worked included Mechanical and Electrical repairs and maintenance
on all of Sawos Cranes as well as installation of new equipment.

01-02-1994 01-11-1994
– Maintenance Supervisor for United Nations Forces. (Bosnia)
– Daily running of the Danish maintenance squadron in Tuzla.
– Supervising Army technicians in maintenance/repair.
– Supervising of security inside our area.
– Supervise and conduct repairs of all kinds in a warzone.

01-07-1991 01-02-1994
– MBM started.
– Supervisor. (Kalgoorlie – W. Australia)
– Mechanical and Electrical repairs/maintenance to all types of machinery in the gold
mining industry.

01-11-1988 01-07-1991
– Forman & Truck driver for JIR (Denmark)

01.03.1988 01.11.1988
– Travel Australia

01.04.1985 01.03.1988
– Military service Danish Army (Denmark and Germany)
– Normal service then sergeant school and the last two years as foreman for 1/1 squadron Jyske -Dragon Regiment maintenance unit.
– Promoted to Sergeant Major by the end of service period.

01-06-1981 01-04-1985
– Contract of apprenticeship mechanical engineering (Fiat Denmark)